|
|
||||||
|
In July 2003, the Public Service Commission of Wisconsin (PSCW) and the state's Department of Natural Resources (DNR) issued their final Environmental Impact Statement (EIS) for the Elm Road Generating Station (ERGS). The EIS was conducted under guidelines of the Wisconsin Environmental Policy Act (WEPA), which are modeled on the federal National Environmental Policy Act (NEPA) guidelines. The agencies' decision to conduct an EIS was not the result of an evaluation and conclusion that the project's potential environmental impacts are significant. Rather, it was dictated by the PSCW's rules that require an EIS for any project involving the construction of an "electric generation facility fueled by coal." The EIS considered background and regulatory requirements, costs and financing issues, the need for baseload capacity in southeast Wisconsin, alternatives to the proposed project, fuel diversity perspectives, the proposed sites and technologies, air emissions, water resources, solid and hazardous waste disposal and remediation, land resources, and community impacts. The EIS also provided a worst-case analysis of the economic and environmental impacts that could result from the construction of a new power plant and its associated facilities. The EIS, however, was not an agency decision about the project and did not make recommendations about approval. The EIS was just one step in the process. Public and technical hearings followed in August and September of 2003. The agencies gave careful consideration to the more than 270 individuals that provided written comments on the ERGS draft EIS. In November 2003, the PSCW issued an order approving parts of the proposed project.
On Nov. 29, 2004, a Dane County Circuit Court vacated the PSCW's approval of our project and sent the case back to the commission for additional proceedings. While we were disappointed with the decision, we were encouraged that the court reaffirmed the need for the power and upheld the sufficiency of the state EIS. The PSCW, DNR, and Wisconsin Energy Corp. filed motions for direct, expedited appeal of the decision with the Supreme Court of Wisconsin. On Jan. 5, 2005, the Supreme Court of Wisconsin granted the motion in a 5-1 vote. Briefs were filed in February and oral arguments were held on March 30, 2005. On June 28, 2005, the Supreme Court of Wisconsin reversed the Dane County Circuit Court's November 2004 decision and reinstated the PSCW's final decision and order in all respects involving construction of the Oak Creek Power Plant expansion. It was a 4-2 decision with Justice Crooks not participating. Justice Bradley dissented and was joined by Chief Justice Abrahamson. Air Permit In February 2005, a Wisconsin Administrative Law Judge issued a decision affirming the DNR’s issuance of the Air Pollution Control and Construction Permit. In the decision, the judge found that DNR did not err on any of the grounds raised by the opponents. Summary of the findings include:
On Feb. 22, 2005, Clean Wisconsin and S.C. Johnson filed a lawsuit with the Dane County Circuit Court seeking judicial review of that decision. The Dane County Circuit Court dismissed on Sept.16, 2005, the appeal of an administrative law judge's decision, affirming the DNR’s issuance of the Air Pollution Control and Construction Permit for the Oak Creek expansion. All parties to this action agreed to the dismissal, including Clean Wisconsin and the Sierra Club. This dismissal is the final resolution of the legal challenges to the WDNR air construction permit. Chapter 30 Permit
In March 2005, the Dane County Circuit Court dismissed an appeal of the Chapter 30 permit based on improper filing procedures by S.C. Johnson and Sierra Club. The opponents appealed the dismissal. In February 2006, the state Court of Appeals affirmed the lower court’s dismissal of the case. Wisconsin Pollutant Discharge Elimination System (WPDES) Permit On April 26, 2005, Clean Wisconsin and SC Johnson filed a lawsuit with the Dane County Circuit Court challenging the DNR’s decision to reissue a WPDES permit. Also, on May 12, 2005, DNR granted the request for a contested case hearing filed by Clean Wisconsin, Sierra Club, and several individuals. In September 2005, the challenge filed with Dane County Circuit Court was dismissed. The DNR’s contested case hearing regarding the permit was held in March 2006. In July 2006, the Administrative Law Judge upheld DNR’s issuance of the WPDES permit. The parties opposing the permit can appeal that decision. The Dane County Circuit Court issued a ruling on March 5, 2007, concerning our WPDES permit. The court did not vacate the permit we received from the DNR. The court affirmed – in important respects – the decision by the DNR to issue the permit and a later decision by a Wisconsin Administrative Law Judge (ALJ), upholding the DNR’s issuance of the permit. The court also remanded certain aspects of the ALJ’s decision for further consideration. The WPDES permit for the Oak Creek site authorizes the operation of the cooling water intake structure for both the existing and added units, using the best technology available to minimize adverse environmental impact. In separate litigation, the Second Circuit Court of Appeals issued a ruling on Jan. 25 remanding to the Environmental Protection Agency (EPA) its rule regarding cooling water intake systems for large utility plants. The suit was brought by several states and environmental groups, including Riverkeeper, an environmental advocacy group. In its March 5 ruling, the Dane County Circuit Court remanded certain parts of the ALJ’s decision so they could be re-evaluated and decided based upon the Jan. 25 federal decision by the Second Circuit Court of Appeals. The Riverkeeper II case, as it is referred to, came out long after the ALJ issued a decision upholding the DNR’s WPDES permit for Oak Creek. On Nov. 29, 2007, the ALJ of the State Division of Hearings and Appeals ruled that the expansion units being built at the Oak Creek site qualify technically as a new facility under the federal Clean Water Act. However, the judge did not vacate the permit for our water intake system nor did he vacate any other permit necessary for the ongoing construction of the Oak Creek units. In his ruling, he also pointed out that, based on the present record, the water intake system may be permittable under the standards that apply for new facilities. The judge directed the DNR to reissue or modify our permit to reflect “best technology available” for complying with the standards applicable to new facilities under state law. We submitted additional information to the DNR that supports the use of our water intake system under these standards. While the process for modifying our water permit proceeded, we continued construction of the Oak Creek units. On Dec. 27, 2007, We Energies filed a petition for review by the Milwaukee Circuit Court of the Nov. 29 decision issued by the ALJ. We Energies is not certain that the ALJ’s decision is final and therefore may be appealed because we must preserve our right to appeal what we believe is an erroneous decision by the ALJ. Subsequently, the city of Oak Creek and the DNR have joined in the proceeding by filing similar petitions in support of preserving our right to appeal the ALJ’s decision. On Feb. 11, 2008, the three petitions for judicial review were consolidated by the Milwaukee County Circuit Court. The court also granted We Energies' motion to dismiss on the grounds that the ALJ’s decision was not a final order; the court also ruled that all issues decided by the ALJ may be judicially reviewed when there is a final agency decision. In May, the WDNR issued a new, draft permit that concluded the new water intake system is the best technology available for both the existing and expansion units at the Oak Creek site. A public hearing was held in June to obtain public comments on the newly proposed modified WPDES permit for the operation of the cooling system. The federal Environmental Protection Agency notified WDNR that it would not object to issuance of the new permit. In August, the WDNR issued a final modified WPDES permit for the existing and expansion units. In addition to the issuance of the permit, We Energies and the owners (WPPI and MGE) of the expansion units at Oak Creek reached an agreement with Clean Wisconsin and Sierra Club—the groups that have been opposing the water intake permit. Under the settlement agreement, the environmental groups will withdraw their opposition to the permit and cooling system. The agreement should bring to a close the ongoing litigation and administrative challenges to the WPDES permit by these groups. The provisions of the agreement include reductions in greenhouse gases, investments in additional renewable energy resources, funding to protect Lake Michigan’s ecosystem and the retirement of older, less-efficient generation. The commitments of the formal agreement include:
These environmental initiatives are the key elements of the settlement agreement with Clean Wisconsin and Sierra Club. Under the settlement agreement, the groups will withdraw all legal opposition to the permit. Army Corps of Engineers Permit |
||||||
Overview | Projects | Regulatory Documents | News | Q&A | Links | Contact Us Home | Top of page This site is best viewed with Netscape 4.0+ or Internet Explorer 4.0+ |